Black Sea gas find to lift Turkey’s output to 25% of EU capacity

Natural gas that Turkey discovered in the Black Sea over the past year is set to provide nearly a 3rd of its domestic needs once it reaches peak output capacity by 2027, the country’s energy minister said.

Black Sea gas find to lift Turkey’s output to 25% of EU capacity

Ankara, September 29 - Neftegaz.RU. Ankara earlier shared its aim to start pumping gas from the Sakarya field to its main grid in 2023, the centennial of the founding of modern Turkey, with sustained plateau production starting in 2027 or 2028, Turkish Daily Sabah analysed.

Unveiling a detailed timeline to bring the nation’s largest-ever natural gas find on stream, Fatih Dönmez told Bloomberg News in an interview that Turkey may be able to start with an initial annual production capacity of 3.5 billion cubic meters (bcm) of gas in 2023.

The eventual aim would be to lift the capacity to around 15 bcm annually within 4 years of the initial production, in what is said to be roughly one quarter of the EU’s output today.
The nation in June announced it had discovered 135 bcm of additional gas in the Amasra-1 borehole in the northern Sakarya field, raising the total discovery in the region to 540 bcm.

Turkey consumes between 45 bcm and 50 bcm of natural gas each year, for which it pays between $12 billion and $15 billion.

The peak output from the Sakarya field would account for over 31% of last year’s demand.
Turkey imported 48.1 bcm of gas last year, up 6% from a year before, of which a 3rd was from Russia.

The gas discovery could alleviate much of the nation’s gas import dependence, most of which mainly comes from Russia, Azerbaijan and Iran via pipelines along with LNG from several countries, including Nigeria, Algeria and the U.S.

Turkey is set to witness a significant rise in the gas demand this year, Deputy Energy & Natural Resources Minister Alparslan Bayraktar said last week, the demand would reach around 60 bcm by the end of the year, adding that soaring natural gas prices would be challenging.

No plans for international firms
Turkey has already initiated production of the pipes that will comprise a pipeline beneath the Black Sea to bring the gas onshore.
The seabed pipeline stretching around 169 km is scheduled to be constructed in 2022 to connect the wells in the region to the main grid.
The gas will be transported to the mainland in 3 phases:
  • The 1st phase of designing the seabed natural gas production systems has been completed
  • The 2nd phase will consist of an onshore gas processing facility at Filyos port, for which the foundation has already been laid
  • The pipelines that are being produced comprise the final phase and will connect those 2 units together
State-run Turkish Petroleum Corporation (TPAO) aims to drill some 40 wells over 4 phases in the Sakarya field.
Ankara has so far insisted it will develop the gas field on its own and has been cool to foreign corporate interest.

Dönmez echoed the views, saying that TPAO has the technical capacity to do it alone and that the government had no plans to invite international oil companies to operate fields.

Follow us on Google News
Advertising at neftegaz.ru

Subscribe to our newsletter

of the best materials Neftegaz.RU

* Incorrect E-Mail Address

By clicking the "Subscribe" button I accept the "Agreement on the processing of personal data"


Advertising at neftegaz.ru