USD 96.0686

0

EUR 105.1095

0

Brent 77.92

-0.84

Natural gas 2.583

-0.04

322

Rosatom: Unit 1 pump station foundation is under construction at Akkuyu NPP Site (Turkey)

Akkuyu NPP is the 1st Nuclear Power Plant in Turkey and the biggest project in the history of Russian-Turkish relations

Rosatom: Unit 1 pump station foundation is under construction at Akkuyu NPP Site (Turkey)

Mersin Province, December 13 - Neftegaz.RU. Construction workers have begun constructing the foundation slab for the pump station of Akkuyu NPP Unit 1.
Reinforcement and installation of formwork is underway at the site; around 400 people are involved in the works.

Pump stations are a complex of facilities designed to supply seawater to the main process shops of the nuclear power plant and are a part of the modern high-tech system of the shore hydraulic engineering structures of Akkuyu NPP.
A total of 4 pump stations will be built, one for each NPP Unit.

The depth of the foundation slab of the pump station is at an elevation of 16.5 m below sea level.
In order to withstand the pressure of seawater, the construction is being carried out under the protection of 1 meter thick concrete diaphragms.

Their walls are reliably held by 3 rows of special fasteners – anchor ties.
There are 384 such ties in the diaphragm walls, 3 rows of 128 in each.
The height of the station building superstructure will be over 11 m, and the basic process equipment and the water intake part will be located underground.

Sergei Butckikh, 1st Deputy CEO of Akkuyu Nuclear, commented the beginning of Unit 1 pump station foundation construction:
  • Development of the foundation pit for the pump station of Unit 1 started in December last year.
  • A whole complex of preparatory work preceded the construction of the pit: filling of the water area, construction of barrier walls, formation of a storm protection embankment
  • After that, a pit 22 m deep was dug and a foundation base – concrete pad – was laid to its bottom to the elevation of -16.5 m
  • Now we proceed from the preparatory stage to the direct construction of the pump station
  • About 30 000 cubic meters of concrete are to be laid into the foundation slab of the building
At the beginning of 2022, the construction of the foundation slab of the pump station for Akkuyu NPP Unit 2 will begin.
Complexly configured water pipelines for the main cooling pumps will be formed there, too.
Sergei Butckikh noted:
  • In terms of complexity, the facility can be compared to the construction of a small hydroelectric power plant, so the design of the pump stations required serious efforts from a team of qualified Russian and Turkish engineers and the construction is in progress using the most advanced technologies
A special formwork will also be used for this, which will allow the work to have the necessary precision.
At the same time, preparations continue for the construction of the pump stations for Akkuyu NPP Units 3 and 4.

Follow us on Facebook
Advertising at neftegaz.ru

Subscribe to our newsletter

of the best materials Neftegaz.RU

* Incorrect E-Mail Address

By clicking the "Subscribe" button I accept the "Agreement on the processing of personal data"


Advertising at neftegaz.ru