Moscow, September 13 - Neftegaz.RU. Oslo-listed oil and gas E&P player BW Energy has started production from the fourth well in its multi-well programme offshore Gabon. The company also kicked off drilling activities at the fifth well in this six-well drilling campaign.
Well performance is in line with expectations with current production at approximately 6,500 barrels per day.
The DHIBM-6H well was drilled as a horizontal well from the MaBoMo production facility to a total depth of 4,125 metres into Gamba sandstone reservoir at the Hibiscus field.
Following completion, the Borr Norve jack-up has commenced drilling operations on the fifth production well DRM-3H.
This will be the first Ruche Gamba well in this drilling campaign.
Carl Krogh Arnet, the CEO of BW Energy said:
- the drilling program progresses as planned with strong HSE results and robust production rates which support our expectations of successive production growth in Gabon into 2024;
- we consistently receive well data confirming excellent reservoir quality, with potential positive implications for Hibiscus reserve estimates.
As previously communicated, DHIBM-3H and -4H have experienced issues with the ESPs (electrical submersible pumps).
Investigations into the cause are ongoing.
DHIBM-4H is currently flowing naturally at 2,800 barrels per day, while DHIBM-3H is temporarily not producing while we continue to work solutions.
Current gross production from the Dussafu license is now approximately 26,500 barrels per day after the fourth Hibiscus well came onstream.
The oil produced at Hibiscus / Ruche is transported by pipeline to the BW Adolo FPSO for processing and storage before offloading to export tankers.