The produced gas is separated and treated directly at the cluster pad. The power center is already providing mechanized oil production at cluster pad 1 and the operation of a drilling rig with electricity. Upon completion of the overhead power transmission line, power supply will be provided to other oil production facilities of the field, reservoir pressure maintenance system, and housing settlement.

The mobile power center will be the main source of energy until completion of the 31 MW gas turbine power plant. The processed associated gas will be supplied to it from the preliminary water discharge unit. After the power plant start-up, the field will be fully supplied with APG power.
Verkhnechonskneftegaz is developing the Verkhnechonskoye oil & gas condensate field, one of the largest in East Siberia, located in the Katangsky District of Irkutsk Region. The North-Danilovskoye field is the 1st field in the new Danilovsky cluster of Rosneft, which also includes South-Danilovskoye, Verkhneicherskoye and Lisovskoye fields.