The basic design solutions for the project, as well as the specifications for feedstock and commercial products, have been agreed upon. The project operator has been issued the technical specifications for connecting the complex to Gazprom's gas transmission system, and the drafting of the design documentation has begun. Engineering surveys have been fully completed at the construction site, which is currently being cleared and prepared for construction works.
Meanwhile, efforts are underway to attract project financing from Russian and international credit institutions.
In March 2019, Gazprom and RusGazDobycha made a decision on the final configuration of the project for a gas processing and liquefaction complex near the settlement of Ust-Luga, with RusKhimAlyans as the project operator.
The complex will be processing ethane-containing gas, which will be supplied via allocated gas pipelines from Gazprom's deposits in the Nadym-Pur-Taz region. A gas chemical facility technologically interconnected with the complex will be constructed by RusGazDobycha.