Local content of facility equipment, as confirmed by the Ministry of Industry and Trade of the Russian Federation, amounts to 68 %.
Alexandr Korchagin, CEO of NovaWind, said:
- The Medvezhenskaya Wind Farm is our 6th completed wind farm, its construction took us less than 12 month from building permit obtained to commissioning
- In 2 years, we have already commissioned 720 MW of wind power capacity in the south of Russia, which undoubtedly confirms technological and organizational efficiency of our projects and solutions
- Now we are facing the next challenge – the construction of wind farms within CSA 2.0 program, and we are fully ready to its requirements in terms of technical and organizational aspects
Until 2027, ROSATOM will put into operation approximately 1.7 GW of wind generation capacity.