Gazprom built 260 km of pipeline between Chayandinskoye field and Power of Siberia interconnector to China

Gazprom is implementing major investment projects in the Far East and Yamal Peninsula on schedule.

Gazprom built 260 km of pipeline between Chayandinskoye field and Power of Siberia interconnector to China

St.Petersburg, May 31 - Neftegaz.RU. Gazprom continues in the east of Russia pre-development operations at the Chayandinskoye field in Yakutia.
In 2020, a gas pre-treatment unit and, inter alia, over 100 gas wells were brought onstream at the field.
The plans for 2021 include an expansion of the gas production well stock.

Chayandinskoye is the primary resource base for the Power of Siberia gas trunkline.
As many as 6 compressor stations are being built on the gas pipeline’s operating section stretching to the Chinese border.

In late 2022, the Kovyktinskoye field will be connected to Power of Siberia.
To that end, Gazprom is actively building a pipeline section from this field to Chayandinskoye.
The work is going on schedule: as of today, 261 out of 803.4 km have been welded, laid, and backfilled.

At Kovyktinskoye, the construction of top-priority infrastructure facilities is underway: foundation works and installation of steel structures at the site of comprehensive gas treatment unit № 2 (CGTU-2) have commenced, the site for CGTU-3 is being prepared, and development drilling continues.

Construction project for the Amur Gas Processing Plant is in full swing:
  • Start-up and commissioning is in progress on 2 production trains of the 1st start-up complex
  • Installation of process equipment is nearly finished on the 3rd and 4th trains
  • large equipment for gas separation is being prepared for assembly on the 5th and 6th trains
  • The project is 76.1 % complete
As part of the expansion of the Sakhalin – Khabarovsk – Vladivostok gas pipeline at the section between Komsomolsk-on-Amur and Khabarovsk, a total of 333 km have been welded, laid, and backfilled to date.
The work is nearing completion.

The development of the gas production center in the Yamal Peninsula continues.
At the Bovanenkovskoye field, additional compressor capacities at gas production site №3 and 6 gas wells will be put into operation in 2021.

At the Kharasaveyskoye field, production wells are being drilled, and the construction of access roads for motor vehicles, sites for a CGTU and a booster compressor station, and a connection gas pipeline is in progress.

Follow us on Google News
Advertising at neftegaz.ru

Subscribe to our newsletter

of the best materials Neftegaz.RU

* Incorrect E-Mail Address

By clicking the "Subscribe" button I accept the "Agreement on the processing of personal data"


Advertising at neftegaz.ru