Belgrade, August 5 - Neftegaz.RU. Gazprom Energoholding, a subsidiary of Russia's Gazprom, has completed the installation of 2 gas turbines at the 200 MW Pancevo gas-fired combined cycle power plant in Serbia, it said.
"The choice of Ansaldo’s gas turbines was motivated by their high efficiency and reliability, as well as the experience of the company in operating similar turbines at the power plants of Gazprom Energoholding in Russia," the director of Gazprom Energoholding Serbia, Aleksandr Varnavskiy, said in the statement.
The next stage of the delivery of basic equipment will be the transportation of 2 waste heat boilers, a steam turbine, and a generator, Gazprom Energoholding said.
In March 2018, the company signed a 40 million EUR ($44.4 million) agreement with Ansaldo for the delivery of two AE64.3A Gas Turbines, WY18Z air-cooled generators and auxiliary systems for the construction of a combined heat and power (CHP) plant in Pancevo.
The commissioning of the power plant is planned for 2020. A total of 180 million EUR will be invested in the construction of the power plant, as the bulk of the funding will be provided by Gazprom, the majority shareholder of NIS.