St. Petersburg, April 23 - Neftegaz.RU. A working meeting between Alexey Miller, CEO of Gazprom, and Sergey Levchenko, Governor of the Irkutsk Region, took place on April 22.
Work is proceeding on schedule as the field is being prepared for commercial production. Specifically, geological exploration is taking place and industrial sites for drilling rigs are being set up along with the required road infrastructure.
The company plans to construct 7 production wells at Kovyktinskoye before the end of this year. Natural gas from the field will start flowing into the Power of Siberia gas pipeline in late 2022.
The meeting participants also discussed issues related to gas grid expansion and NGV infrastructure development in the Irkutsk Region.