Saad Sherida Al-Kaabi, CEO of Qatar Petroleum, said:
- This contract provides for the expansion of existing infrastructure required to ensure the safe loading and on-time delivery of our LNG cargoes to our international customers across the globe
- Its scope includes 3 LNG tanks and 3 LNG loading berths for NFE, and options for 2 LNG tanks and 1 LNG berth for NFS project and all associated pipes, lines and loading lines
- We look forward to working with Samsung to deliver this important component of the North Field Expansion project in a safe, timely and efficient manner
- I am delighted that the detailed engineering activities under the contract will take place in Qatar, thus leveraging the growing technical capabilities for the development of major projects in the country
On February 8, 2021, QP awarded the EPC contract for the construction of 4 LNG mega-trains with associated facilities to Chiyoda Technip Joint Venture.
The award of this contract for the expansion of the LNG storage and loading facilities represents yet another important milestone on the road to substantially increase the Qatar’s LNG production capacity.
Both contracts represent the culmination of front-end engineering and design work that began in early 2018.
When completed, the NFE Project will increase the Qatar’s LNG production capacity from 77 million to 110 tonnes per annum (MTPA).
The 2nd phase of the planned LNG expansion, the North Field South (NFS) Project, will further increase Qatar’s LNG production capacity from 110 MTPA to 126 MTPA by 2027.