USD 103.95

+0.68

EUR 110.4804

+1.92

Brent 73.35

-0.18

Natural gas 3.458

-0

421

Atommash delivered the reactor pressure vessel for power Unit 1 to Akkuyu NPP (Turkey)

Atommash delivered the reactor pressure vessel for power Unit 1 to Akkuyu NPP (Turkey)

Volgodonsk, November 11 - Neftegaz.RU. Equipment of major importance for Power Unit 1 – the reactor pressure vessel (RPV) – has been delivered to the Akkuyu NPP site, having covered a distance of 3,000 km. The RPV is large-size equipment, which, at the NPP operation stage, accommodates nuclear fuel, and where a nuclear reaction involving liberation of a high amount of heat takes place under high pressure.

The RPV, which weighs 330 tons, and is 4.5 m in diameter and 12 meters high, was manufactured at Atommash, the Volgodonsk branch of AEM-technology. The manufacture took nearly 3 years. More than 750 production operations were carried out during the production of the reactor pressure vessel.

The RPV for Akkuyu NPP and its parts successfully passed more than 300 quality control tests at various stages of manufacture. It took 20 days to deliver the RPV from the special quay of Atommash at Tsimlyanskoye Reservoir to the Eastern Cargo Terminal at the Akkuyu NPP site.

"Construction and installation works at Akkuyu NPP site are progressing at a very good pace; Some key structural components have been mounted in the 1st power unit - the 2nd tier of the internal containment, the cantilever truss and the supporting truss; the corium collecting and cooling device and the reactor dry shielding have been installed as per design position. In late September, 4 steam generators for Power Unit 1 were delivered to the Eastern Cargo Terminal; today we are receiving the core of the 1st power unit of the NPP - the nuclear reactor pressure vessel. Upon completion of all necessary customs procedures, the reactor pressure vessel will pass the incoming inspection", said Sergei Butckikh, Director of the NPP under construction.

According to all regulatory requirements, the reactor vessel will be subject to incoming inspection. A special commission, which has been established for this purpose, will check the completeness and quality of engineering and accompanying documentation, and will perform a thorough inspection of the item itself using various equipment. As the next step, the reactor pressure vessel will be handed over for installation.

The Nuclear Regulatory Authority (NRA) and independent inspection organizations accredited by it conducted inspections and checks at all stages of manufacture of the reactor pressure vessel at Atommash plant. All work on the site are also being carried out under the supervision of the NRA and independent inspection organizations accredited by the Authority within the scope of the Inspection Activity Plan.

Follow us on Facebook
Advertising at neftegaz.ru

Subscribe to our newsletter

of the best materials Neftegaz.RU

* Incorrect E-Mail Address

By clicking the "Subscribe" button I accept the "Agreement on the processing of personal data"


Advertising at neftegaz.ru