Rosatom: Steam generators for power unit No.1 delivered to Akkuyu NPP

Rosatom: Steam generators for power unit No.1 delivered to Akkuyu NPP

Mersin Province (Turkey), October 2 - Neftegaz.RU. 4 steam generators for Power Unit 1 weighing 365 tons each (net weight without packaging is 355 tons) unshipped at the Eastern Cargo terminal. The shipment of equipment started on August 22 in Volgodonsk at the Atommash plant.

The steam generators manufactured for the 1st nuclear power plant in Turkey were transported in closed holds secured by chains. To unload steam generators from the ship, a large Liebherr LR 1800 crawler crane was assembled at the NPP site.

The steam generators were unloaded from the ship to a storage area for heavy weights where the equipment and all its components will have to go through incoming control.



This procedure will be carried out by a commission of specialists from the Akkuyu Nuclear divisions from the equipment acceptance control department, reactor shop, metal control and technical control department. Specialists of the equipment manufacturer of the Atommash Branch of AEM Technologies in Volgodonsk, the developer of the reactor plant design of OKB “Gidropress” and the key contractor Titan2 IC İctas İnsaat Anonim Şirketi also participate in the incoming control.

The check includes an assessment of the quality and quantity of the supplied materials including an inspection for the absence of defects, check of the conservation quality as well as the completeness and correctness of the accompanying documentation.

Steam generators are the main equipment of the reactor primary circuit. Akkuyu NPP project includes 4 power units with VVER-1200 reactors of generation 3+; each unit will be equipped with 4 steam generators.

The steam generator is a 1st class safety equipment. It is a horizontal cylindrical vessel with 2 elliptical bottoms. The manifold collectors for coolant supply and discharge are located in the middle part: the coolant at the Akkuyu NPP is chemically demineralized water. In the upper part of the body there is a space where steam is generated, and in the lower part there is a heat exchange surface, which consists of 11,000 stainless tubes.

If all tubes of one steam generator are folded in length, their total length will be 148.5 km. The tube diameter is 16 mm, length varies from 11 to 17 m. The tube ends are fixed to 2 manifold collectors. The length of the apparatus is approximately 15 meters, diameter is more than 4 m.

Steam generators are installed after the columns have been erected, embedded fittings and supports are installed; these works precede the start of the main circulation pipeline welding.

To read the news in Russian.

Follow us on Google News
Advertising at neftegaz.ru

Subscribe to our newsletter

of the best materials Neftegaz.RU

* Incorrect E-Mail Address

By clicking the "Subscribe" button I accept the "Agreement on the processing of personal data"


Advertising at neftegaz.ru