STUK’s experts positively assessed the task management functionality on the corporate portal, noted the progress in the development of interface management and documentation management processes, and mentioned well managed technical arrangements for remote inspection.
During the inspection, 3 out of the existing 5 requirements were closed. RAOS Project will continue working on the 2 regulatory requirements remaining open.
Based on 3-day discussions, STUK opened a new requirement related to project management system. STUK stressed the need to address actively project management issues related to the next phase of the project – the construction phase. STUK wants to assess project management organization throughout the full life cycle of the NPP construction – including 6-month transition period, construction and installation phase and NPP start-up works.
The Hanhikivi-1 project incl. the construction of a single-unit NPP featuring a modern Russian-designed VVER-1200 Generation III+ reactor with a capacity of 1200 MW. Hanhikivi-1 NPP construction will be carried out on the Hanhikivi Peninsula in the Finnish region of Northern Ostrobothnia. To date, the project is at the stage of licensing and preparatory works at the NPP construction site.