Voronezh region, August 2 - Neftegaz.RU. On July 31 at 19:23, the reactor of the innovative Unit 2 of Novovoronezh Phase II for the 1st time was brought to the design power capacity.
Over 2 months, specialists have successfully raised the reactor power capacity. Tests of the equipment were carried out at 40%, 50%, 75% and 90% of the rated power. It was raised up to 100% also under the normal conditions. No issues to equipment operation in different modes were revealed.
The stage of gaining 100% power capacity envisages about 100 different tests and measurements which will take about 2 months. Then, the program of the final 15-day tests will start. Its completion will confirm that the equipment and process systems of the new power unit operate as designed.
To read the article in Russian.