Voronezh region, June 5 - Neftegaz.RU. Unit 2 of Novovoronezh Phase II with a Generation III+ reactor has started the stage of pilot commercial operation (PCO). The plant is a branch of the Rosenergoatom Concern which is part of Power Division of Rosatom.
The PCO stage will end after successful testing at all power levels, including the nominal power (100%) and completion of all commissioning trials of the power unit.
This will be followed by an inspection of Rostechnadzor of the completed power unit for the design conformance and by issue of the corresponding statement. Unit 2 is expected to be put in commercial operation late 2019.