Trillion Energy Adds Additional Wells To SASB Work Program

Trillion Energy is planning to add three sidetrack wells to the development program for the SASB gas field, increasing the total number of wells at the Black Sea project from 17 to 20.

Trillion Energy Adds Additional Wells To SASB Work Program

Moscow, January 11 - Neftegaz.RU. Trillion Energy said it had identified several additional opportunities to increase production at the SASB gas field offshore Türkiye during 2023 by adding the three sidetrack wells to its development program.

Eleven of these well operations are anticipated to occur during 2023, which will result in rapidly increased quantities of natural gas production during the year. Side-track wells and workovers take relatively less time than long reach directional wells (10-30 days vs 45-48 days for a new drill), thus, allowing for an increase in the number of planned wells for 2023.

The side-tracks cost about $3 million less per well than long reach directional wells as they utilize a large section of an existing well bore where a “window” is then milled out from the existing casing to create the new well. The South Akcakoca2 well was successfully drilled as a side-track during 2022.

The opportunity for the additional three side-track wells arose using experience gained from the successful recompletion of initial wells drilled during 2022 as well as other geological works. Production volume, log evaluations, perforation intervals and gas production behavior has now been evaluated to calculate the estimated remaining gas reserves in the East Ayazli Gas field and Akkaya Gas field.

The Company anticipates similar production volumes from the added sidetracks compared to other new wells planned in the drilling program.

Natural gas sale prices for January 2023 are about US $27/MCF, historically high pricing for the Turkiye region.


Arthur Halleran, CEO of Trillion, stated:
  • During 2023 we are focusing on using the Uranus rig to increase production through new wells, sidetracks and workovers;
  • An added benefit of drilling side-tracks from existing well boreholes is that they are already tied into the pipeline and production facility, so once drilled and completed the wells are immediately put on production;
  • We are currently in the process of getting our partner’s feedback on the proposed side-tracks;
  • We are pleased to have developed a work program which permits continuous drilling over the year to enable us to exit 2023 with 13 wells.

Follow us on Facebook
Advertising at neftegaz.ru

Subscribe to our newsletter

of the best materials Neftegaz.RU

* Incorrect E-Mail Address

By clicking the "Subscribe" button I accept the "Agreement on the processing of personal data"


Advertising at neftegaz.ru