It was noted at the meeting that the progress of the project is currently at 61.9 %. At the 1st and 2nd production trains of the GPP, which are going to come onstream in 2021, installation of the core equipment is completed, process pipelines are being installed and provided with thermal insulation, and start-up and commissioning activities are underway.
Process pipelines are also being installed at the 3rd production train, while the installation of steel structures and foundations for large equipment is being finished at the 4rth train. At the 5th and 6th trains, foundations are being poured while piperacks and steel structures are being assembled. More than 28,000 workers and engineers are working at the construction site.
With the opening of the navigation season, large equipment can now be delivered by sea and river vessels. This year, 43 units of equipment weighing a total of 7,700 tons will be brought to the Amur GPP's wharf.

Construction of the Svobodny TPP, which has a capacity of 160 MW and will provide the GPP with heat and electricity, is ongoing: its main building is completed, the steam generators are in place, and work is underway on the steam turbines and auxiliary equipment.
The commercial product supply system of the Amur GPP will include the Helium Tank Logistics Center based near the city of Vladivostok. It will be the world's largest hub for the servicing of thermally-insulated helium containers, which will deliver liquid helium to the global market.
It is planned that the Logistics Center will have a capacity to perform upward of 4,500 process operations with containers per year. At present, construction of the hub's main production buildings is nearing completion, and preparations for the installation of core process equipment are in progress.
To read the article in Russian.




