Santos announced that first production from the Halyard-2 infill well has commenced

The well is online six weeks ahead of schedule and is now producing.

Santos announced that first production from the Halyard-2 infill well has commenced

Moscow, February 13 - Neftegaz.RU. Santos, one of Western Australia’s largest domestic gas suppliers, today announced that first production from the Halyard-2 infill well has commenced.

The well is online six weeks ahead of schedule and is now producing.
This will supply an incremental 65 mmscf/d into Varanus Island.
Further, it will convert approximately nine mmboe of sales gas and condensate to 2P developed reserves.

Santos Managing Director and Chief Executive Officer Kevin Gallagher said this is a valuable short-cycle capex project, delivering incremental low-cost volumes into the portfolio through to 2027, and supporting a reduction in unit production costs in 2025.

Kevin Gallagher said:

  • this project demonstrates Santos’ commitment to our disciplined low-cost operating model and our focus on efficient execution of our projects and strong operational results in 2025.

Подпишитесь

Follow us on Google News
Advertising at neftegaz.ru

Subscribe to our newsletter

of the best materials Neftegaz.RU

* Incorrect E-Mail Address

By clicking the "Subscribe" button I accept the "Agreement on the processing of personal data"


Advertising at neftegaz.ru