The next 2 modules have been loaded onto a transport ship and are on transit to Murmansk.
Overall, 14 modules will be delivered from contractors' shipyards for the 1st LNG train.
The Arctic LNG 2 project is progressing on schedule, and the successful delivery of the 1st modules represents an important milestone towards launching the project on time.
NOVATEK has a 60% stake in Arctic LNG 2, with the remaining shareholders comprising:
The participants of Arctic LNG 2 approved a FID for the project in September 2019. - France's Total (10%)
- China's CNPC (10%), China's CNOOC (10%)
- a consortium of Japan's Mitsui and Jogmec with the final 10% stake
Capital expenditures to launch the project at full capacity is estimated at $21.3 billion equivalent.